Householder, full, prior approval or lawful development certificate? A plain guide to choosing the right route and preparing a strong submission.
Householder applications cover extensions and alterations to a single house. Full planning applications cover new buildings, conversions, flats and commercial work. Prior approval applications apply to certain permitted development rights. A Lawful Development Certificate confirms that existing or proposed work is lawful without needing permission.
Statutory determination periods are generally 8 weeks for householder and minor applications and 13 weeks for major applications, after the council validates the submission. Validation itself can take several weeks if information is missing.
A typical submission includes the application form and fee, a site location plan, existing and proposed plans, elevations and sections, and, where relevant, a Design and Access Statement, Heritage Statement, daylight assessment, tree survey or flood risk assessment. Each council publishes a local validation list.
Pre-application advice from the council is optional but often worthwhile for sensitive sites. It identifies objections early and shapes the design before the formal application.
If an application is refused, options include revising and resubmitting, or appealing to the Planning Inspectorate — within 12 weeks of the decision for householder appeals and 6 months for most other appeals.
This guide is general information for England and is not legal or planning advice for a specific property. Rules change and councils apply local policy, so check the position for your address before acting.